Document details
High risk construction work covered by this SWMS
Regulation 291 of the model WHS Regulations lists 18 classes of high risk construction work. Tick every class this SWMS covers. If no class applies, you do not need a SWMS, though a JSA or risk assessment is still worth doing.
- Risk of a person falling more than 2 metres
- Work on or near energised electrical installations or services
- Work in or near a confined space
- Work in or near a shaft or trench deeper than 1.5 metres, or a tunnel
- Demolition of a load-bearing element of a structure
- Work involving the disturbance of asbestos
- Structural alteration or repair requiring temporary support to prevent collapse
- Tilt-up or precast concrete work
- Work on, in or adjacent to a road, railway or other traffic corridor in use
- Work in an area with movement of powered mobile plant
- Work in or near water or other liquid with a risk of drowning
- Work on or near chemical, fuel or refrigerant lines
- Work on or near pressurised gas distribution mains or piping
- Work in an area that may have a contaminated or flammable atmosphere
- Use of explosives, diving work, artificial extremes of temperature, or work on a telecommunication tower
Job steps, hazards and controls
Break the work into steps in the order they happen. Every class ticked above must appear as a hazard against at least one step. Choose controls from the top of the hierarchy first: eliminate, then substitute, isolate and engineer, then administrative controls, with PPE last.
| Job step | Hazards | Risk rating | Control measures | Person responsible |
|---|---|---|---|---|
Plant, permits and PPE
- Plant and equipment to be used are listed, with inspection and maintenance records current
- High risk work licences (e.g. scaffolding, rigging, crane operation) held and sighted
- Permits obtained where needed: confined space entry, hot work, excavation, electrical isolation
- Underground and overhead service locations obtained before breaking ground
- Exclusion zones and barricading planned and marked
- PPE required for each step listed and available on site
- Safety data sheets available for hazardous chemicals used in the work
- Emergency equipment on site: first aid, fire extinguisher, rescue gear for confined space or fall arrest work
Consultation and sign-on
Workers carrying out the work must be consulted when the SWMS is prepared, and every worker must sign on before starting. Anyone who joins the job later signs on at induction.
| Name | Role | Signature | Date |
|---|---|---|---|
Monitoring and review
If the work is not being carried out in accordance with this SWMS, it must stop. Resume only after the SWMS is followed, or after it is revised and the crew re-briefed.
Review and revise the SWMS whenever the work changes, the way it is carried out changes, or a control proves ineffective. Keep the SWMS until the high risk construction work is completed. If a notifiable incident occurs in connection with the work, keep it for at least 2 years after the incident.