Scope note
Some jurisdictions set a specific height that triggers particular duties for certain kinds of work, and others impose duties wherever a fall could cause injury regardless of height. Do not work from a remembered trigger height. Record the requirement that applies to you below, from Safe Work Australia and your state WHS regulator or your own procedure, and apply the stricter of that and your risk assessment.
Low falls injure and kill people. A fall from a step ladder onto a hard floor is a common source of serious head injury, so do not treat short heights as automatically out of scope.
Job details
Step 1 - Can the work at height be avoided
This is the only control that removes the risk. Exhaust it before moving on.
- Can the task be done from the ground, for example with extendable tools
- Can the item be lowered, or brought to ground level, for the work
- Can the work be designed out, for example by relocating a serviceable item
- Can remote inspection replace physical access, for example a camera or drone survey
- If the answer to all of these is no, record why and continue
Step 2 - Select the access method
Work down this list. Choose the highest option that is reasonably practicable, not the one that is quickest to set up.
- Permanent platform, walkway or stair with fixed guardrail
- Scaffold with guardrails, erected and inspected by a competent person
- Elevating work platform or scissor lift, operated by a licensed or trained operator
- Mobile scaffold tower, correctly assembled, braced and with wheels locked
- Fall prevention system: guardrails, covers, or a travel-restraint system that stops the worker reaching the edge
- Fall arrest system: harness and lanyard that arrests a fall in progress, with rescue arranged
- Ladder, for light, short-duration work only, with three points of contact maintained
Step 3 - Equipment checks
- Ladder is the right type and rating, undamaged, on firm level ground, secured, and extends far enough above the landing
- Scaffold has a current inspection tag, is complete, and has not been modified by anyone unauthorised
- Elevating work platform has current inspection and maintenance records, and the operator holds the required licence
- Guardrails, toe boards and covers are in place, secure and rated for the load
- Anchor points are rated, certified, in date and appropriate for the direction of loading
- Harness is in date, inspected before use, correctly sized and correctly fitted
- Lanyard and energy absorber are in date, undamaged, and the length is correct for the available fall clearance
- Fall clearance below has been calculated, so the worker cannot reach the ground or an obstruction before arrest
- Tools are tethered, and the exclusion zone below is barricaded against falling objects
Step 4 - Conditions
- Weather is suitable: wind, rain, ice, heat and lightning all assessed, with stop conditions agreed
- Lighting is adequate for the work and the access route
- Surfaces have been assessed for fragility, including roof sheeting, skylights and corroded decking
- Fragile surfaces are covered, barricaded or clearly marked
- Overhead hazards identified, especially powerlines, with the required clearance maintained
- Access route to the work position is safe, including getting on and off the platform
- Public, staff and vehicles are excluded from the area below
Step 5 - Rescue plan
If a fall arrest system is used, a rescue plan is required before work starts. A worker suspended in a harness needs to be recovered quickly, and waiting for emergency services may not be fast enough.
- Rescue method decided and equipment available on site
- Rescuers identified, trained and present for the duration
- Nobody is working at height alone where rescue depends on a second person
- Method of raising the alarm confirmed, including how to call 000
- Suspension intolerance understood, and the plan aims to recover the person promptly
- Rescue plan briefed to everyone before work starts
Sign-off
| Role | Name | Signature | Time |
|---|---|---|---|
| Supervisor | |||
| Worker 1 | |||
| Worker 2 |