Project and document details
Risk assessment
Score likelihood and severity from 1 to 5 and multiply. Anything scoring 15 or above needs further controls before work starts; re-score after controls to show the residual risk.
| Hazard | Who might be harmed and how | Likelihood (1-5) | Severity (1-5) | Score | Controls |
|---|---|---|---|---|---|
Method statement - sequence of work
Number each stage in the order it will happen on site, from arrival and set-up through to demobilisation. A competent person who has never seen this job should be able to follow it.
| Stage | Description of work | Plant and equipment | Key controls at this stage |
|---|---|---|---|
Plant, people and supporting documents
- Plant and equipment listed, with statutory inspection records (e.g. LOLER, PUWER) current
- Operatives hold the required competency cards or tickets (e.g. CSCS, CPCS, IPAF, PASMA) as applicable
- Minimum PPE stated for each stage of the work
- COSHH assessments attached for any hazardous substances used
- Manual handling assessment attached where loads cannot be designed out
- Working at height: a rescue plan is in place, not just fall arrest equipment
- Temporary works design checked and approved where required
- Site rules and permits from the principal contractor obtained before starting
- Waste, housekeeping and public protection arrangements defined
Emergency arrangements
Briefing and sign-on
Everyone carrying out the work must be briefed on this RAMS before starting and sign below. Re-brief anyone who joins later, and everyone after any revision.
| Name | Company | Signature | Date |
|---|---|---|---|